5.5 Completion of Level 2


Top level Canadian International School Chapter 5 - The Permanent Campus at Nam Long Shan Road (¡§the Site¡¨)

Phase I proved to be tremendously popular for all concerned and CDNIS continued with its growth.

Plans were therefore made to add additional classrooms and computer teaching facilities in Level 2. Space was allowed (but unfinished) for these extra facilities within the structure that was built in Phase I. An interior fitting-out type contract was issued in March of 2000, to the contractor - Pat Davie, who did an excellent job in providing finishing work for some of the areas in Phase I. Works on Level 2 were completed in August and ready for use before the students returned for the fall term.